Installation
Transport System Installation
MagneMover LITE User Manual
15
Rockwell Automation Publication MMI-UM002E-EN-P - March 2016
Leveling the MagneMover LITE
Once the stand assembly is complete and the transport system is properly located ensure all
sections of the beam are level.
1.
Establish a datum for the system (interface to existing equipment, etc.).
2.
Use a laser level to identify the datum throughout the installation area as shown in
Figure 5-5: System Leveling
3.
Ensure all sections of the beam are level and correctly referenced to the datum.
A.
Place a machinist square vertically on the beam at each location where a foot is
located below the beam and reference the laser beam.
B.
Adjust the feet on the legs as required to reach the required height using a
14 mm Hex wrench.
C.
Lock the feet into position by tightening the jam nut against the leg using a
17 mm Hex wrench.
D.
Repeat for each foot.
Laser Level
12” Machinist Square