Figure 6-226 Drilling holes and installing expansion sleeves
(1) M12 bolt
(2) Spring washer
(3) Flat washer
(4) Expansion sleeve
(5) Expansion nut
(6) Concrete floor
Step 3 Combine cabinets.
1. Remove the screws preinstalled on the copper bars in power cabinet 2 and
store them for future use.
Figure 6-227 Removing the preinstalled screws
2. Move the UPS cabinets to the installation positions.
3. Remove the power distribution covers from power cabinets 1 and 2.
Figure 6-228 Removing the covers