Figure 6-50 Installing AC power cables
●
One power source
If the mains input and bypass input share a power source, you do not need to
remove the copper bar between the mains and bypass input terminals or
connect the bypass input power cable.
Step 4 Install battery cables.
NO TE
The number and colors of cables are for reference only.
The figure uses the cable connection between the UPS and the SmartLi as an example.
Connect battery cables to each SmartLi.
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
116