Figure 6-133 Installing AC power cables
Step 6 Install battery cables.
NO TE
The number and colors of cables are for reference only.
The figure uses the cable connection between the UPS and the SmartLi as an example.
Connect battery cables to each SmartLi.
Figure 6-134 Installing power cables between the UPS and the SmartLi
(1) Connect the ground cable of the battery string or its BBB box to the battery PE of the UPS
or the ground bar in the equipment room based on the site survey.
Step 7 Install UPS top frames (No. 14–17).
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)