Make sure the transducer wires have good contact with the terminal block and the
terminal block screws are tight.
32. Ensure the Junction Box O-ring seal is correctly installed and adjust if necessary.
33. Reinstall the Junction box cover plate with the four hex head bolts and lock washers.
Tighten bolts with a 7/16 inch (11 mm) wrench.
34. Apply power to the meter.
35. Connect to the meter with MeterLink. Open the Meter Monitor (Detailed) view and
verify the meter is acquiring data, the transducers have good signals and flow
profiles for the chords are displayed and run the Zero Flow Calibration Wizard;
select the
Calibrate
→
Zero Calibrate menu
and generate the report. Then, collect
and save a Maintenance log to show the “as left” condition of the meter. Or use
AMS
™
Device Manager or a HART
®
Field Communicator and select
Overview
→
Zero Calibration
→
Start menu
or
Service Tools
→
Maintenance
→
Zero
Calibration
→
Start
.
36. Close your application connection (MeterLink, AMS
™
Device Manager or HART
®
Field Communicator).
37. Reinstall the shroud:
•
•
•
•
38. If required, install the security seals through the hex bolts in the Junction box cover
Seal the Junction Box for remote mount electronics option
).
This completes the procedure for replacing the transducers on meters with remote
mount transmitter electronics option.
3.8
Meter electronics replacement
The following procedure should be performed by a qualified service technician or trained
personnel. Observe all warning before starting this procedure.
Meter maintenance
Maintenance and Troubleshooting Manual
April 2022
00809-0100-3812
90
Emerson.com/Rosemount