Vacuum drying
•
- Use a vacuum pump which can evacuate
up to –14.6 psi or less.
[Procedure] Operate the vacuum pump for evacuation for
2 hours or more using both liquid pipe and gas pipe until the
vacuum pressure reaches –14.6 psi or less. Leave the air
conditioner at –14.6 psi or less for 1 hour or more, and
confi rm that the vacuum pressure indicated by the vacuum
gage does not increase.
(If the vacuum pressure increases, the system may contain
moisture or have leakage.)
If there is a possibility of moisture remaining in the piping
(for example, when there is a possibility of dew condensation
inside the piping because the piping work was performed in
the rainy season or over a long period of time, or when rainwa-
ter may have entered the piping during the work)
Perform evacuation described above for 2 hours (vacuum
drying), pressurize the air conditioner up to 7 psi (vacuum
break) with nitrogen gas, then evacuate the air conditioner
using the vacuum pump for 1 hour to achieve –14.6 psi or less
(vacuum drying).
(If the vacuum pressure does not reach –14.6 psi or less even
after evacuation for 2 hours or more, repeat vacuum break and
vacuum drying.) Leave the air conditioner in the vacuum status
for 1 hour or more, and confirm that the vacuum pressure
indicated by the vacuum gauge does not increase.
Additional refrigerant charge
6-7
WARNING
To avoid injury always use protective gloves and eye protec-
•
tion when charging refrigerant.
To avoid injury do not charge with unsuitable substances.
•
Use only the appropriate refrigerant.
NOTE
Refrigerant cannot be charged until fi eld wiring has been
•
completed.
Refrigerant may only be charged after performing the air-
tight test and the vacuum drying (see above).
When charging refrigerant into the system, take care that its
maximum allowable charge is never exceeded, in view of the
danger of liquid hammer.
Refrigerant containers shall be opened slowly.
To avoid compressor breakdown, do not charge the refriger-
ant more than the specif
i
ed amount to raise the condensing
pressure.
This outdoor unit is factory charged with refrigerant.
•
Charge the additional refrigerant calculated by the formula
•
below.
Additional charging
amount =
Liquid piping length
× 0.036 +
Additional charging
depended on type
of indoor unit
(lb.)
(ft.)×0.036 A
(lb.)
Indoor unit
FAQ
FCQ
FHQ
FTQ
Additional charging
A (lb.)
0
1.54
Record the additional amount to the label stuck on the back of
front panel.
Charge the refrigerant to the liquid pipe in its liquid state.
•
Since R410A is a mixed refrigerant, its composition changes
if charged in a state of gas and normal system operation
would no longer be assured.
Before fi lling, check whether the tank has a siphon attached
•
or not.
How to fi ll a tank with a siphon attached.
There is a siphon tube
inside, so there is no need
to turn the tank upside-down.
Fill with the tank upright.
Other ways of fi lling the tank
Fill with the tank upside-down.
After the vacuum drying is fi nished, charge the additional
•
refrigerant in its liquid state through the liquid stop valve
service port.
Taking into account following instructions:
Check that gas and liquid stop valves are closed.
1.
Charge the specifi ed amount of refrigerant.
2.
If the outdoor unit is not in operation and the total amount
•
cannot be charged, follow the procedures for additional
refrigerant charge shown below.
Make sure to use installation tools you exclusively use on
•
R410A installations to withstand the pressure and to prevent
foreign materials from mixing into the system.
Procedures for charging additional refrigerant.
•
Nitrogen
Dotted lines
represent
field piping
Cylinder
Stop valve service port
Vacuum pump
Weighing
scale
Charge hose
R410A
Pressure
reducing
valve
Outdoor unit
Indoor unit
Liquid line
Gas line
(Siphon system)
Valve A
See the “Cautions on service” label on the back of the front
panel for the settings for operation after replenishing refriger-
ant.
Open the gas line stop valve (leaving the liquid line stop
1.
valve, valve A in the diagram above, close) and perform the
operation to add the refrigerant.
Once the appropriate amount of refrigerant is in, press the
2.
confi rmation button (BS3) on the outdoor unit PC board
(A2P), and stop operation.
Open the stop valves quickly (both liquid and gas line
3.
valves).
(This must be done quickly to avoid the possibility that the
pipe might burst.)
Summary of Contents for SkyAir RZQ-P Series
Page 1: ...Cooling Only 60Hz Heat Pump 60Hz RZR P RZQ P 9 series EDUS281120_a AMERICAS ...
Page 31: ...Dimensions and service space EDUS281120_a 30 RZR P RZQ P 9 BRC2A71 Unit in 3D047341 ...
Page 33: ...Dimensions and service space EDUS281120_a 32 RZR P RZQ P 9 BRC7E818 for FAQ 3D049736 Unit in ...
Page 34: ...EDUS281120_a Dimensions and service space RZR P RZQ P 9 33 BRC4C82 for FBQ 3D049611 Unit in ...
Page 38: ...EDUS281120_a Dimensions and service space RZR P RZQ P 9 37 3D064213A ...
Page 39: ...Dimensions and service space EDUS281120_a 38 RZR P RZQ P 9 3D064213A ...
Page 41: ...Dimensions and service space EDUS281120_a 40 RZR P RZQ P 9 3D047381B ...
Page 47: ...Wiring diagrams EDUS281120_a 46 RZR P RZQ P 9 FAQ18PVJU FAQ24PVJU 3D046039D ...
Page 61: ...Safety devices list EDUS281120_a 60 RZR P RZQ P 9 8 3 FAQ FAQ18PVJU FAQ24PVJU 4D047085B ...
Page 91: ...Capacity tables EDUS281120_a 90 RZR P RZQ P 9 RZR36PVJU RZR42PVJU 3D071685 ...
Page 92: ...EDUS281120_a Capacity tables RZR P RZQ P 9 91 RZQ36PVJU9 RZQ42PVJU9 C 3D047383B ...
Page 101: ...Sound Levels Reference EDUS281120_a 100 RZR P RZQ P 9 FBQ18PVJU FBQ24PVJU FBQ30PVJU FBQ36PVJU ...
Page 102: ...EDUS281120_a Sound Levels Reference RZR P RZQ P 9 101 FBQ42PVJU ...
Page 104: ...EDUS281120_a Sound Levels Reference RZR P RZQ P 9 103 RZQ42PVJU9 RZR42PVJU 4D072769 ...