Cold Asphalt (too stiff to circulate)
a.
Check the parking brake is set and the asphalt tank gauge reads
above the fire line.
b.
Open exhaust stack.
c.
Start burners as needed.
d.
Monitor temperature to circulate as soon as possible.
e.
Follow instructions for warm asphalt circulation above.
CAUTION:
TO AVOID EQUIPMENT DAMAGE, HEAT THE MATERIAL
SLOWLY IF MOISTURE IS PRESENT IN THE TANK. THE
MATERIAL TEMPERATURE WILL NOT RISE ABOVE
212°F UNTIL THE MOISTURE IS GONE.
Do not circulate material in the spray bar at first. As much as 20%
of the heat developed in the asphalt can be dissipated due to heat
losses in the spray bar.
Heating with Diesel Fired Burners
WARNING:
POTENTIAL FIRE OR EXPLOSION HAZARDS EXIST
WHEN OPERATING THE BURNERS. FAILURE TO
FOLLOW THE BURN OPERATION SAFETY PROCEDURES
COULD RESULT IN SEVERE BURNS, INJURY OR DEATH.
WARNING:
IF A BURNER GOES OUT, DO NOT ATTEMPT TO RE-LIGHT
IT FOR AT LEAST TWO (2) MINUTES. THIS WILL ALLOW
THE VAPORS TO DISSIPATE FROM THE FLUE. FLIP THE
SWITCH TO THE “COOL-DOWN” POSITION DURING THIS
TIME. FAILURE TO COMPLY COULD RESULT IN A
POTENTIAL EXPLOSION HAZARD AND CAUSE SEVERE
BURNS, INJURY OR DEATH.
NOTE:
The burners must be turned on sequentially as listed in burner
operation section
Summary of Contents for BC-502/CRC
Page 1: ...INSTRUCTION MANUAL Model BC 502 CRC Asphalt Distributor ...
Page 42: ...BC 502 CRC 42 ...
Page 43: ...43 ...
Page 69: ...69 ...
Page 87: ...87 Stage 1 ...
Page 151: ...151 Figure 13 INNER WING ASSEMBLY Figure 14 HYDRAULIC SYSTEM ...
Page 152: ...152 Figure 15 REAR PANEL ASSEMBLY ...
Page 154: ...154 Figure 17 PUMBING AND VALVE ASSEMBLY ...
Page 156: ...156 Figure 19 PUMP DRIVE ASSEMBLY ...
Page 157: ...157 Figure 20 PRODUCT PUMP ...
Page 158: ...158 Figure 21 SIDE CONTROL BOX SCHEMATIC ...
Page 159: ...159 Figure 22 CAB CONSOLE SCHEMATIC ...
Page 160: ...160 Figure 23 VALVE BOX SCHEMATIC ...
Page 161: ...161 Figure 24 REAR CONTROL BOX SCHEMATIC ...
Page 162: ...162 Figure 25 REAR CONTROL BOX PROPANE SCHEMATIC ...
Page 163: ...163 Figure 26 HYDRAULIC LAYOUT ...
Page 164: ...164 Figure 27 HYDRAULIC SCHEMATIC ...