Preventive Maintenance Schedule
The minimum recommended service checks and intervals for your asphalt
distributor are as follows:
Daily
1.
Check hydraulic oil level (ISO 46).
2.
Check filter vacuum gauge after initial warm up.
3.
Check gland packing for leaks:
a.
Cargo Pump (if applicable).
b.
Equalizer Valve.
c.
Spread/Circulate Valve.
d.
Tank Gauge.
4.
Inspect the spray bar for leaks at the nozzles, valve stems and
swing joints.
5.
Check hydraulic cylinders for seal leaks.
6.
Check for air leaks.
7.
Drain the air tanks.
8.
Inspect for correct operation of wing limit switches.
9.
Test the burner safety switch. Burner should not work if brakes
are not set.
10.
Clean the bar and suction screens (or as needed).
11.
Clean the spray bar with an approved cleaning agent at the end of
the day.
12.
As needed during the day, spray the shafts of the hydraulic
cylinders and the air cylinders with PAM (or equivalent) to prevent
asphalt from building up.
13.
When the computer is turned on, verify that the calibration
numbers are correct.
14.
Make certain that the bar and wing latches are in good condition
for travelling.
15.
Make sure taillights and markers are clean, unobstructed and in
working order.
Summary of Contents for BC-502/CRC
Page 1: ...INSTRUCTION MANUAL Model BC 502 CRC Asphalt Distributor ...
Page 42: ...BC 502 CRC 42 ...
Page 43: ...43 ...
Page 69: ...69 ...
Page 87: ...87 Stage 1 ...
Page 151: ...151 Figure 13 INNER WING ASSEMBLY Figure 14 HYDRAULIC SYSTEM ...
Page 152: ...152 Figure 15 REAR PANEL ASSEMBLY ...
Page 154: ...154 Figure 17 PUMBING AND VALVE ASSEMBLY ...
Page 156: ...156 Figure 19 PUMP DRIVE ASSEMBLY ...
Page 157: ...157 Figure 20 PRODUCT PUMP ...
Page 158: ...158 Figure 21 SIDE CONTROL BOX SCHEMATIC ...
Page 159: ...159 Figure 22 CAB CONSOLE SCHEMATIC ...
Page 160: ...160 Figure 23 VALVE BOX SCHEMATIC ...
Page 161: ...161 Figure 24 REAR CONTROL BOX SCHEMATIC ...
Page 162: ...162 Figure 25 REAR CONTROL BOX PROPANE SCHEMATIC ...
Page 163: ...163 Figure 26 HYDRAULIC LAYOUT ...
Page 164: ...164 Figure 27 HYDRAULIC SCHEMATIC ...