Due to the fact that no fault theoretically equals infinite fault resistance and
viewing this only plots unreliable values, it is better to view the fault
conductance, which is zero in this case.
As no fault is applied, the measured fault conductance must be close to zero.
Confirm this by viewing the graph.
It may be necessary to zoom in or out to properly view the measurements. For
instructions on this, see
6.
Apply for example 10kΩ fault resistance.
6.1. Make sure that it is correctly measured.
6.2. Try to change the
Viewed quantity
to
Fault resistance
as 10kΩ is
relatively small.
You should be able to measure approximately 10kΩ here. If you choose
to view fault conductance, the measurement corresponds to
approximately 1×10
-4
Mho.
7.
Apply another known fault, say 1kΏ and verify that it is measured correctly.
8.
When you are completely sure that the function measures correctly, stop the
measurements and remove any applied faults.
Previously it was verified that the function measures correctly by applying
known faults and observing the graph during monitoring. Besides measuring
the fault size a trip indication is required when a large fault is measured to
prevent that a damage to the generator occurs. To allow the specific function
to issue a trip indication, it must first be enabled:
8.1. Select the
Enable Function Tripping
button in the ICT toolbar.
8.2. Choose
Yes
in the pop-up message.
ICT now writes this to IED.
8.3. By default the trip level is set to 1kΩ. In other words, if the fault
resistance is lower, then the function issue trips.
9.
Verify the measurements by applying various faults.
Trip indication shall be visible in the ICT toolbar.
10. Verify that TRIP and ALARM signals are connected to tripping/alarming/
signaling/communication in accordance with the scheme design.
It is very important that the Function Tripping is Enabled under the
following situations:
•
After completion of the calibration step
•
Before leaving the ICT Tool
11.7
Auditing
During installations, calibrations and commissions the ICT generates reports for
each of the steps and collects them under the Auditing tab. See the procedures
below on how to view and delete reports as well as generate logs from reports.
Section 11
1MRK 502 029-UEN A
Calibrating injection based 100% stator earth fault protection
130
Installation and commissioning manual
Summary of Contents for Relion 670 series
Page 1: ...Relion 670 series Generator protection REG670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 92: ...86...
Page 96: ...90...
Page 102: ...96...
Page 108: ...102...
Page 112: ...106...
Page 126: ...120...
Page 140: ...134...
Page 150: ...144...
Page 234: ...228...
Page 238: ...232...
Page 250: ...244...
Page 259: ...253...