See section
2.
Carefully press the sealing strip (1) around the IEDs collar. Cut the end of the
sealing strip a few mm to long to make the joining point (5) tight.
The sealing strip is delivered with the mounting kit. The strip is long enough
for the largest available IED.
3.
Insert the IED into the opening (cut-out) in the panel.
4.
Add and lock the fasteners (2) to the IED.
Thread a fastener into the groove at the back end of the IED. Insert and
lightly fasten the locking screw (4). Next, thread a fastener on the other side
of the IED, and lightly fasten its locking screw. Lock the front end of the
fastener in the panel, using the M5x25 screws.
Repeat the procedure with the remaining two fasteners.
5.3.3
19” panel rack mounting
5.3.3.1
Overview
All IED sizes can be mounted in a standard 19” cubicle rack by using the for each
size suited mounting kit which consists of two mounting angles and fastening
screws for the angles.
The mounting angles are reversible which enables mounting of IED size 1/2 x 19”
or 3/4 x 19” either to the left or right side of the cubicle.
Please note that the separately ordered rack mounting kit for side-by-
side mounted IEDs, or IEDs together with RHGS cases, is to be
selected so that the total size equals 19”.
When mounting the mounting angles, be sure to use screws that
follows the recommended dimensions. Using screws with other
dimensions than the original may damage the PCBs inside the IED.
Section 5
1MRK 502 029-UEN A
Installing the IED
34
Installation and commissioning manual
Summary of Contents for Relion 670 series
Page 1: ...Relion 670 series Generator protection REG670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 92: ...86...
Page 96: ...90...
Page 102: ...96...
Page 108: ...102...
Page 112: ...106...
Page 126: ...120...
Page 140: ...134...
Page 150: ...144...
Page 234: ...228...
Page 238: ...232...
Page 250: ...244...
Page 259: ...253...