Installation checklist
Installation checklist
Checking the installation
Check the mechanical and electrical installation of the drive before start-up. Go
through the checklist below together with another person. Read chapter
Safety
on
page
11
of this manual before you work on the drive.
Check
MECHANICAL INSTALLATION
The ambient operating conditions are within allowed limits. (See
Mechanical installation:
Checking the installation site
on page
23
as well as
Technical data
:
Losses, cooling data and
noise
on page
142
and
Ambient conditions
on page
147
.)
The drive is fixed properly on an even vertical non-flammable wall. (See
Mechanical
installation
on page
23.
)
The cooling air flows freely. (See
Mechanical installation
:
Free space around the drive
on
page
23
.)
The motor and the driven equipment are ready for start. (See
Planning the electrical
installation
:
Checking the compatibility of the motor and drive
on page
30
as well as
Technical
data
:
Motor connection data
on page
144
.)
ELECTRICAL INSTALLATION
(See
Planning the electrical installation
on page
29
and
Electrical
installation
on page
39
.
)
For ungrounded and corner-grounded systems: The internal EMC filter is disconnected
(screw EMC removed).
The capacitors are reformed if the drive has been stored over a year.
The drive is grounded properly.
The input power voltage matches the drive nominal input voltage.
The input power connections at U1, V1 and W1 are OK and tightened with the correct torque.
Appropriate input power fuses and disconnector are installed.
The motor connections at U2, V2 and W2 are OK and tightened with the correct torque.
The motor cable, input power cable and control cables are routed separately.
The external control (I/O) connections are OK.
The input power voltage cannot be applied to the output of the drive (with a bypass
connection).
Terminal cover and, for NEMA 1, hood and connection box, are in place.
Summary of Contents for ACS150 series
Page 4: ......
Page 5: ......
Page 15: ...14 Safety ...
Page 19: ...18 Introduction to the manual ...
Page 39: ...38 Planning the electrical installation ...
Page 51: ...50 Installation checklist ...
Page 57: ...56 Start up and control with I O ...
Page 69: ...68 Control panel ...
Page 79: ...78 Application macros ...
Page 160: ...L Q M 0 I II D I II I I ro I m D en m D D Q Q f 3AFE68633931 A 0 Frame size R2 IP20 INEMA 1 ...
Page 161: ...ji 4 I 5 I 6 4 J ...
Page 162: ......
Page 163: ...160 Dimension drawings ...
Page 169: ...166 Appendix Process PID control ...
Page 171: ...168 ...