Supervision
Commissioning Example: Supervision Scheme 50BF
Object to Be Tested:
Test of the breaker failure protection (Supervision Scheme 50BF).
Necessary Means:
Current source;
Ammeter; and
Timer.
When testing, the applied test current must always be higher than the
tripping threshold
»I-CBF«. If the test current falls below the threshold
while the breaker is in the “Off” position, no pickup will be generated.
Procedure
(Single-Phase):
For testing the tripping time of the CBF protection, a test current has to be higher than the threshold value of one of
the current protection modules that are assigned to trigger the CBF protection. The CBF trip delay can be measured
from the time when one of the triggering inputs becomes active to the time when the CBF protection trip is asserted.
To avoid wiring errors, checked to make sure the breaker in the upstream system switches off.
The time, measured by the timer, should be in line with the specified tolerances.
Successful Test Result:
The actual times measured comply with the setpoint times. The breaker in the higher-level section switches off.
Re-connect the control cable to the breaker!
525
MRU4
DOK-HB-MRU4-2E
Содержание High PROTEC MRU4
Страница 1: ...Manual Voltage Relay MRU4 Software Version 3 0 b DOK HB MRU4 2E Revision B English...
Страница 51: ...Installation and Connection Ethernet RJ45 Terminals 51 MRU4 DOK HB MRU4 2E 1 8 TxD TxD RxD n c n c RxD n c n c...
Страница 64: ...Navigation Operation Navigation Operation 64 MRU4 DOK HB MRU4 2E 1 2 3 5 7 6 8 10 9...