Protective Elements
Reconnection Module
Available Elements:
ReCon
The
reconnection
function after a mains decoupling is based on the requirements of the VDE AR-N 4120
1
and the
German directive „Erzeugungsanlagen am MS-Netz“
2
.
To monitor the
reconnection
conditions after a mains decoupling, a
reconnection
function has been implemented in
parallel to the decoupling functions.
Mains voltage (phase to phase) and frequency are the main criteria for
reconnection
. Always the mains side voltage
(line to line) at the generator circuit breaker (mains side) has to be evaluated.
The
reconnection
function is only one of the system functions for mains decoupling and return synchronizing.
The reconnection element is tied to decoupling functions like the
Q->&U<-element and other integrated decoupling
functions like under-/overvoltage, under-/overfrequency. The reconnection can be triggered by up to 6 decoupling
elements or via digital input signals, logic functions or via scada (communication system).
After a trip of the circuit breaker at the PCC by the decoupling function,
reconnection
has to be done manually.
Danger of asynchronously
reconnection
:
The
reconnection
function does not substitute a synchronizing device.
Before connecting different electrical networks, synchronism has to be
secured.
After decoupling by the
Q->&V< module or other decoupling functions, like V</V<<, V>/>>, f</> the
reconnection
release signal for
reconnection
the circuit breaker of the power generating unit will be blocked for a preset time
interval (default setting 10 min.). This is to wait until all switching operations are completed. The automatic
reconnection must not be executed before mains voltage and frequency are inside the acceptable bands (quasi
permanent) that means within the admissible limit values for a preset, settable time.
The purpose of the reconnection function is to reconnect a decoupled energy resource safe to the mains/grid.
Release logic for the Generator Circuit Breaker
If the PCC circuit breaker has tripped the reconnection has to be done manually. A special blocking logic is not
necessary.
If a power generating unit should be reconnected by the generator circuit breaker
the voltage transformers have to be installed at the mains side of the circuit
breaker.
1
Technische Anschlussregeln für die Hochspannung (VDE-AR-N 4120)
2
Technische Richtlinie „Erzeugungsanlagen am Mittelspannungsnetz“, Richtlinie für Anschluss und
Parallelbetrieb von Erzeugungsanlagen am Mittelspannungsnetz, Ausgabe Juni 2008, BDEW Bundesverband der
Energie- und Wasserwirtschaft e.V., siehe Kap. 3.2.3.2 – Blindleistungs-Unterspannungsschutz Q->&U<
455
MRU4
DOK-HB-MRU4-2E
Содержание High PROTEC MRU4
Страница 1: ...Manual Voltage Relay MRU4 Software Version 3 0 b DOK HB MRU4 2E Revision B English...
Страница 51: ...Installation and Connection Ethernet RJ45 Terminals 51 MRU4 DOK HB MRU4 2E 1 8 TxD TxD RxD n c n c RxD n c n c...
Страница 64: ...Navigation Operation Navigation Operation 64 MRU4 DOK HB MRU4 2E 1 2 3 5 7 6 8 10 9...