Commissioning and optimization (software)
7
7.1
Commissioning sequence
The sequence in which the software of a frequency converter in an ET 200 station is
commissioned depends on how complex the drive application is, and on the automation
structure.
The basic drive functions and the higher-level controller are commissioned first and are then
specialized, optimized and the drive application generated.
The parameters and settings that are located during this process can be used for standard
commissioning, if required.
Requirements
A prerequisite for software commissioning is functional hardware that has been
commissioned according to the chapter entitled "Commissioning (hardware)".
A drive configuration has been generated for the converter and the motor has been
commissioned with the factory settings.
Procedure
1.
First commissioning and optimization
–
Frequency converter/motor combination
–
Drive application
–
Communication between the S7 CPU and frequency converter
–
Fail-safe functions
2.
Standard commissioning
Transferring the parameters and settings to other frequency converters
Содержание Simatic ET 200pro FC
Страница 1: ......
Страница 2: ......
Страница 12: ...Table of contents ET 200pro FC 12 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 158: ...Technical data 10 2 General ambient conditions ET 200pro FC 158 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 180: ...Appendix A 3 Standards ET 200pro FC 180 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 190: ...List of abbreviations acronyms B 1 Abbreviations ET 200pro FC 190 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 192: ...Glossary ET 200pro FC 192 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 195: ......
Страница 196: ......