Series commissioning and operation
8.2 Series commissioning and replacement of the frequency converter
ET 200pro FC
142
Operating Instructions, 07/2016, A5E01100763B AC
WARNING
All the data interfaces, including the digital and analog interfaces, are reinitialized for the
series commissioning. This will interfere temporarily with data transfer or will cause the
digital outputs to switch over.
Before embarking on series commissioning, you must secure any dangerous loads.
To do this, proceed as follows:
•
Lower the load to the ground or
•
Secure the load using the motor holding brake.
Standard commissioning sequence with STARTER
1.
Configure all frequency converters to be involved in standard commissioning with the
same application ID.
2.
Commission the first frequency converter.
3.
Upload from frequency converter to the PC: Frequency converter parameters are saved
on the PC.
4.
Download from PC to the frequency converter: The saved parameters are transferred to
other frequency converters.
Note
In the case of a download with STARTER, all the necessary parameters (with the
exception of fail-safe parameters) will be downloaded to the frequency converter.
See also
Содержание Simatic ET 200pro FC
Страница 1: ......
Страница 2: ......
Страница 12: ...Table of contents ET 200pro FC 12 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 158: ...Technical data 10 2 General ambient conditions ET 200pro FC 158 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 180: ...Appendix A 3 Standards ET 200pro FC 180 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 190: ...List of abbreviations acronyms B 1 Abbreviations ET 200pro FC 190 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 192: ...Glossary ET 200pro FC 192 Operating Instructions 07 2016 A5E01100763B AC ...
Страница 195: ......
Страница 196: ......