Creating a new project
Step
Procedure
Result
1
Double-click
on the symbol
.
(if the STEP 7 Assistant starts, cancel this.)
The SIMATIC Manager is opened.
2
Select
File > New
.
Enter
"My First Project“
into the dialog box, Project.
In the dialog box, select the path
„LW:\Siemens\Step7\S7proj“
.
Click on
OK
.
Your new project is displayed.
3
Select
Insert > Station > SIMADYN D station
.
The "
SIMADYN D station“
hardware object
is inserted.
1.3
Defining the hardware
The SIMADYN D subrack structure is entered in STEP 7
(HW Config).
Step
Procedure
Result
4
Select the hardware object
"SIMADYN D station“
and select
Edit > Open object
.
HW Config
is called-up.
5
Open it, if required, the hardware catalog
with
View > Catalog
.
The hardware catalog with all of the available
family of modules is opened.
6
Select the
SR6
from the
SIMADYN D
family of modules and Catalog
Subracks
and drag it to the (upper) window
The subrack is displayed with six slots.
7
Locate them one after the other
>CPU Modules >PM5
at slot 1
>Expansion Modules >IT41
at slot 2
>Slot covers >SR81
at slots 3 to 6
The subrack is equipped.
8
Open the properties dialog box of the PM5
CPU module with
Edit > Object properties
.
The PM5 dialog box with general module
information and the setting registers for
addresses, basic clock cycle, cyclic tasks
and interrupt tasks are displayed.
9
Select the basic sampling time T0 (in this
case: 1 ms) under the
basic clock cycle
tab.
Click on the
cyclic tasks
tab and set the
sampling time T1 to 2 ms and T2 to 4 ms.
Click on
OK
.
The required sampling times are entered.
The properties dialog box is closed.