5.22
SEL-387-0, -5, -6 Relay
Instruction Manual
Date Code 20170601
Metering and Monitoring
Through-Fault Event Monitor
To reset the cumulative through-fault count, reset cumulative I
2
t, and clear out
the stored through-fault events, execute the
TFE C
(clear) or
TFE R
(reset)
command. The relay responds:
=>
TFE R <Enter>
Clear Through Fault Event Buffer
Are you sure (Y/N) ?
Y <Enter>
Clearing Complete
=>
Changing Global setting ETHRU also has the same effect as executing the
TFE C
or
TFE R
command.
Preload the following cumulative through-fault count and I
2
t values:
➤
10 through-fault counts
➤
147.8 (kA)
2
seconds on A-phase
➤
303.5 (kA)
2
seconds on B-phase
➤
237.9 (kA)
2
seconds on C-phase
Execute the
TFE P
command to preload these values. The relay responds:
=>
TFE P <Enter>
Number of Through Faults Preload = 2?
10 <Enter>
Winding 1 Total I-squared-t Preload (kA^2 seconds, primary):
A-phase = 1.783?
147.8 <Enter>
B-phase = 88.270?
303.5 <Enter>
C-phase = 6.610?
237.9 <Enter>
Are you sure (Y/N) ?
Y <Enter>
If the
TFE
command is then executed, the response shows the new preloaded
values (the through-fault events at bottom are not disturbed):
=>
TFE <Enter>
XFMR 1 Date: 02/12/04 Time: 18:59:49.130
STATION A
FID=SEL-387E-X300-V0-Z102102-D20040211
Number of Through Faults: 10 Last Reset: 02/10/04 19:56:22
Winding 1 Total I-squared-t (kA^2 seconds, primary):
A-phase B-phase C-phase
147.800 303.500 237.900
# Date Time Duration IA IB IC
(seconds) (A, primary max)
1 02/14/04 18:59:22.244 5.002 241 4158 260
2 02/11/04 11:37:55.495 30.834 220 241 451
Deriving Cumulative
I
2
t Values for
Preloading
If cumulative I
2
t values need to be derived for preloading, refer first to
Through-Fault Calculation on page 5.20
to see how individual I
2
t calculations
are made (even though this referenced subsection refers to how the relay does
the calculation automatically, the same approach is still valid for “hand”
calculations). In the referenced subsection, notice how the example 6000 A
(6 kA) fault value is handled in the calculation, so that the resultant comes out
in units of (kA)
2
seconds. All the individual I
2
t calculations, for the
corresponding faults on a specific phase, are then summed together to create a
cumulative I
2
t value that can then be preloaded for that phase. Use the
previously discussed
TFE P
command to preload the cumulative I
2
t values for
each phase.
Содержание SEL-387-0
Страница 6: ...This page intentionally left blank ...
Страница 12: ...This page intentionally left blank ...
Страница 50: ...This page intentionally left blank ...
Страница 200: ...This page intentionally left blank ...
Страница 248: ...This page intentionally left blank ...
Страница 380: ...This page intentionally left blank ...
Страница 422: ...This page intentionally left blank ...
Страница 440: ...This page intentionally left blank ...
Страница 458: ...This page intentionally left blank ...
Страница 516: ...This page intentionally left blank ...
Страница 540: ...This page intentionally left blank ...