SunTouch
®
Control System Installation Steps Summary
The recommended SunTouch
®
Control System installation steps are:
Review, prepare and install SunTouch Power Center (pages 49): Review high voltage connections.
Prepare and install the SunTouch Control System Power Center at the equipment pad. AC power for
SunTouch should be provided from the main-panel circuit breaker located at the house.
Remove SunTouch Control System Power Center knockouts, install conduit and low voltage wire
to the Power Center (page 53).
Install Auxiliary Relays and Valve Actuators (page 58-60): Install auxiliary relays, valve actuators, and
connect actuator cables to the SunTouch control system motherboard (VLV A, VLV B, or VLV C).
Install Temperature Sensors and Heat Thermostat (page 61): Install water and air sensors. Connect
sensor cable plugs to the SunTouch Control System motherboard.
Optional Equipment - Connecting IntelliChlor
®
Salt Chlorine Generator and IntelliFlo
®
VS and
VF Pumps (page 75-77): Connect the IntelliChlor (SCG) and IntelliFlo VS or IntelliFlo VF pumps
communication cable to the SunTouch control system motherboard to connector COM PORT.
SunTouch Control System Start-up (page 65): Perform a system start-up procedure.
Setting up SunTouch Control System after equipment installation using main menu (page 66):
Configure the SunTouch control system control panel via the main menu for installed equipment.
Required Tools
• 3/16 in. diameter drill (for mounting the SunTouch Control System Power Center)
• 3/8 in. diameter drill (for mounting water temperature sensor)