241-1501-240 5.2S2
Installing a BITS cable
Install a BITS cable from the timing source directly to the alarm/BITS
module or to a prefabricated cable assembly to enable network
synchronization with the node.
Prerequisites
•
You must be familiar with “Safety considerations and best practices”
(page 53).
•
The prefabricated alarm/BITS timing cables that you can connect to
include:
— NTHR75
— NTHW75
— NTPN81
•
When your timing connection requires a cable that connects directly to
the alarm/BITS module or connects to one of the prefabricated timing
cable assemblies, you need a custom-made BITS cable. See “Making a
BITS cable” (page 635).
•
The BITS wire pairs from the site’s B reference timing source plug into
the J3 receptacle and the A reference timing source plug into the J4
receptacle. J3 and J4 are located on the alarm/BITS module at the rear of
the NEBS 2000 frame. The alarm/BITS module receptacle connects to a
male 9-pin D-sub (DB9) connector directly from a site source or as part
of the prefabricated cable assemblies. For a redundant timing setup
(using both the A and the B timing references), a DB9 connector is
needed for each reference at J3 and J4.
Procedure steps
1
Test the signal strength of the site source at the end of the cable before
connecting it to J 3 and J4 of the alarm/BITS module. The signal strength
must be within the range indicated in “Making a BITS cable” (page 635).
If the signal is not within the range, fix the problem between the point of
test and the site source. Depending on the length of cable from the site
source, you many need a thicker gauge cable to ensure the signal
strength.
Содержание Passport 15000
Страница 1: ...Passport 15000 20000 Hardware Installation Maintenance and Upgrade 241 1501 240 ...
Страница 2: ......
Страница 4: ......
Страница 6: ...6 Publication history 241 1501 240 5 2S2 ...
Страница 32: ...32 Contents 241 1501 240 5 2S2 ...
Страница 48: ...48 About this document 241 1501 240 5 2S2 ...
Страница 52: ...52 Chapter 1 Overview of hardware tasks 241 1501 240 5 2S2 ...
Страница 70: ...70 Chapter 2 Safety considerations and best practices 241 1501 240 5 2S2 ...
Страница 84: ...84 Chapter 4 Alarm BITS module 241 1501 240 5 2S2 ...
Страница 94: ...94 Chapter 5 CP and FP cables 241 1501 240 5 2S2 ...
Страница 178: ...178 Chapter 11 Initial switch hardware installations 241 1501 240 5 2S2 ...
Страница 182: ...182 Chapter 12 MAC address module 241 1501 240 5 2S2 ...
Страница 216: ...216 Chapter 14 Power and ground hardware of a Passport 15000 or 20000 241 1501 240 5 2S2 ...
Страница 872: ...872 Chapter 17 Hardware procedures 241 1501 240 5 2S2 ...
Страница 873: ......