9-16
Performing tests using a DCSM
411-2051-500
Draft
00.01
November 1999
How to invoke the MRLP test
Before the test is run the appropriate CTTPARMS tuple must be datafilled
with the correct criteria. With the CTTPARMS tuple correctly datafilled and
selected through CTTGROUP, the test may be initiated either manually from
the MAP level (VCH or CTT) or automatically using CTTSCHED. Procedure
9-9 outlines the manual method of invoking the MRLP test.
Figure 9-8
MRLP Test results MTX302 Log
Refer to the DualMode 800 Enclosure Troubleshooting Guide, 411-2051-900,
for more information of the fields in MTX303 Log. Below are the descriptions
of the fields of MTX302 which give the actual measure results:
Tx PWR
- The measured forward RF power in dBm
Troubleshooting action
If the test fails then it should be repeated for verification. Should the test still
fail the following hardware components may be at fault:
•
TRU (ACH & VCH)
•
Power Amplifier
Procedure 9-10
Initiating the MRLP test
Step
Action
Observation
1
Go to the MAP level of the MTX radio (VCH) to be
tested:
(example)
MAPCI;MTC;MTX;CELL 100;VCH
2
Post the radio to be tested:
(example)
POST 2
3
Invoke the MRLP test on the posted radio:
TST MRLP
The MTX will respond
that the test is underway.
4
Wait for the results of the MRLP test. The MTX
will display them once the test is complete.
See Figure 9-8.
5
If the results fails check to see if the CTTPARMS
fields are correctly set. Then repeat the test to
verify the failure.
MTX302 JUN29 12:12:12 2500 CTT RF POWER TEST
CELL: 20x TEST: MRLP VCH: 10 HW: BST
VPL : 0 Tx PWR: -50 dBm EXP PWR: -58 dBm
Q1PWR: 0 dB Q2PWR: 2 dB
PASS
Содержание DualMode 800
Страница 2: ......
Страница 4: ......
Страница 6: ...vi Publication history Nortel Networks Confidential 411 2051 500 Draft 00 01 November 1999...
Страница 82: ...2 20 Periodic maintenance 411 2051 500 Draft 00 01 November 1999...
Страница 90: ...3 8 Test equipment and precautions 411 2051 500 Draft 00 01 November 1999...
Страница 100: ...5 6 Master Oscillator tests 411 2051 500 Draft 00 01 November 1999...
Страница 106: ...6 6 Antenna and transmission line tests 411 2051 500 Draft 00 01 November 1999...
Страница 116: ...8 4 Alarm Control Unit ACU tests 411 2051 500 Draft 00 01 November 1999...
Страница 138: ...10 2 ICRM tests 411 2051 500 Draft 00 01 November 1999...
Страница 200: ...12 10 Enclosure maintenance 411 2051 500 Draft 00 01 November 1999...
Страница 208: ...A 8 Appendix A Frequency table 411 2051 500 Draft 00 01 November 1999...
Страница 215: ......