Performing tests using a DCSM
9
Introduction
The DualMode Cell Site Monitor (DCSM) can operate in either stand-alone
mode or directed mode. In stand-alone mode, the handset on the front panel is
used to conduct manual calls. In directed mode, the MTX assumes control of
the DCSM to perform a variety of non-obtrusive tests of the site. The MTX
directed tests on the CCH, VCH, and LCR can be invoked from the respective
level of the MAP position. Additionally from the CTT level VCH tests can be
initiated with the option of testing a number of Devices Under Test (DUT) in
sequence. The tests can also be set-up to be automatically run using the
scheduler feature of Table CTTSCHED.
By making a call to the DCSM in the stand-alone mode or performing tests at
the MTX in the directed mode, the Control Channel (CCH) and Voice
Channels (VCH) of a cell site can be verified to be operating correctly.
Stand-alone mode tests
In stand-alone mode the mobile unit in the DCSM functions in the same
manner as a subscriber mobile telephone in the cellular system. For this
reason, the mobile unit in the DCSM has to be activated in the same manner
as a subscriber mobile telephone. The cellular system will not recognize the
mobile unit or allow it to function unless the programming on the Numerical
Assignment Modules (NAM) is completed. Refer to Chapter 1, Cell site
operation, for the programming of the NAMs.
In stand-alone mode the DCSM acts as a subscriber mobile registered in the
partition. Once the mobile of the DCSM has acquired and locked onto a CCH
in the partition it can be used to make a call through test through the handset
of the mobile. Making a call verifies that the system is up and running.
Stand-alone ACCH/DCCH selection
When a partition is equipped with both an ACCH and a DCCH do the following:
1. select NAM 4 and enter the programming selection mode
Содержание DualMode 800
Страница 2: ......
Страница 4: ......
Страница 6: ...vi Publication history Nortel Networks Confidential 411 2051 500 Draft 00 01 November 1999...
Страница 82: ...2 20 Periodic maintenance 411 2051 500 Draft 00 01 November 1999...
Страница 90: ...3 8 Test equipment and precautions 411 2051 500 Draft 00 01 November 1999...
Страница 100: ...5 6 Master Oscillator tests 411 2051 500 Draft 00 01 November 1999...
Страница 106: ...6 6 Antenna and transmission line tests 411 2051 500 Draft 00 01 November 1999...
Страница 116: ...8 4 Alarm Control Unit ACU tests 411 2051 500 Draft 00 01 November 1999...
Страница 138: ...10 2 ICRM tests 411 2051 500 Draft 00 01 November 1999...
Страница 200: ...12 10 Enclosure maintenance 411 2051 500 Draft 00 01 November 1999...
Страница 208: ...A 8 Appendix A Frequency table 411 2051 500 Draft 00 01 November 1999...
Страница 215: ......