Issue 1.2
UNIVERGE SV9100
4 - 8
Installing the SV9100 Blades
2.2.3.2
Installing GCD-PRTA (T1/PRI) Blades
The GCD-PRTA (T1/PRI) Interface blade uses the first block
of 30 consecutive trunks.
For example, if an GCD-4COTA and GPZ-4COTE blade is
installed for trunks 1~8, the GCD-PRTA (T1/PRI) blade
automatically uses trunks 9~32. If GCD-4COTA and
GPZ-4COTE blades are installed for trunks 1~8 and 17~24,
the GCD-PRTA (T1/PRI) blade uses trunks 25~54. The
GCD-PRTA (T1/PRI) blade cannot use trunks 9~16 (even if
available) since they are not part of a consecutive block of
30 trunks.
2.3
Remove an Extension or Trunk Blade
Any blade,
EXCEPT
the ones listed below can be removed while the system is
powered up. To remove any of the blades listed below, the system
must first
be powered down
.
GCD-CP10
GPZ-BS10
and
GPZ-BS11
GPZ-IPLE
To remove an extension/trunk blade with the system running:
1.
When LED 2 is extinguished, all extensions/trunks are idle.
2.
Loosen the thumb screws on either side of the blade and pull it out of the
chassis.
2.4
Uninstalling a Blade Slot Through Software
The installer can turn off (busy out) and delete (remove from software) blade
slots in the Controlling and Expansion Chassis in programming for port
renumbering or to replace it with a different blade. Deleting a blade may affect
blade slot programming capability. Refer to Program 90-05 in the Univerge
SV9100 Programming Manual for detailed programming information.
Содержание Univerge SV9100
Страница 1: ...System Hardware Manual Issue 1 2 January 2015...
Страница 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 40: ...Issue 1 2 UNIVERGE SV9100 1 16 Introduction to SV9100...
Страница 44: ...Issue 1 2 UNIVERGE SV9100 2 4 SV9100 System Specifications Figure 2 1 SV9100 System Block Diagram...
Страница 100: ...Issue 1 2 UNIVERGE SV9100 3 28 Installing the SV9100 Chassis Figure 3 36 Anchor Bolt from Wall 9 5 Chassis...
Страница 105: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 3 33 Figure 3 42 Brackets Small Batt Box...
Страница 154: ...Issue 1 2 UNIVERGE SV9100 3 82 Installing the SV9100 Chassis...
Страница 185: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 31 Figure 4 8 Connecting a IPLA Daughter Board to a Network PC...
Страница 199: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 45 Figure 4 12 Installing the GPZ 4LCA Daughter Board...
Страница 239: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 85 Figure 4 24 Control Signal Connection...
Страница 259: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 105 NOTES...
Страница 260: ...Issue 1 2 UNIVERGE SV9100 4 106 Installing the SV9100 Blades...
Страница 325: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 5 65 Figure 5 57 Sticker Braille L KIT Sheet 2...
Страница 412: ...Issue 1 2 UNIVERGE SV9100 5 152 Installing DT Series Digital and IP Multiline Terminals...
Страница 418: ...Issue 1 2 UNIVERGE SV9100 6 6 Installing SV9100 Optional Equipment Figure 6 5 PGD 2 U10 ADP Connection Diagram...
Страница 425: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 6 13 Figure 6 11 Setting the PGD 2 U10 ADP for a Door Box...
Страница 426: ...Issue 1 2 UNIVERGE SV9100 6 14 Installing SV9100 Optional Equipment Figure 6 12 Installing a Door Box...
Страница 438: ...Issue 1 2 UNIVERGE SV9100 6 26 Installing SV9100 Optional Equipment Figure 6 17 PGD 2 U10 ADP Connections...
Страница 475: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 6 63 Figure 6 64 Power Failure Connector CN3 Shown on GCD 4COTA Blade...
Страница 476: ...Issue 1 2 UNIVERGE SV9100 6 64 Installing SV9100 Optional Equipment...
Страница 477: ...THIS PAGE IS INTENTIONALLY LEFT BLANK...