Load management program
92 / 156
6.7 Installation menu
Press the
[Installation]
button to show the “Installation menu”.
Menu to enter details necessary to parameterize a working KeContact M10 system.
There are two variants of the installation process:
First time installation:
This is the initial installation of a Charge Point. After the installation, the Charge Point is operational.
Please find t
he detailed description of the installation process in chapter “First time installation ->
Installation menu”.
Update installation:
An update installation is required if a Wallbox is added, the IP address set by the DIP switches of the
Wallbox is changed or the capacity of the connection to the power grid is changed.
Installation menu