Procedure
Step 1
On the home screen of the power unit LCD, choose
Power Unit N Info.
>
Maintenance
>
Battery Maint
.
Step 2
Tap
Start
next to
Capacity Test
to start a capacity test.
Figure 5-14
Starting a capacity test
The capacity test automatically stops in any of the following cases:
The battery discharge voltage reaches the end of discharge (EOD) voltage plus 0.01 V.
The load fluctuation exceeds 10%.
An alarm is generated.
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is complete. The test
data is used as capacity test data. Save the capacity test data record with the largest discharge capacity in
a month as the capacity test data for the month. A maximum of recent 36 capacity test records can be
saved.
----End
5.6.4 Test Data Download
Procedure
Step 1
On the WebUI of the power unit, choose
Query
>
Logs
, choose logs that need to be exported
from the
Log
drop-down list box, and click
Query
.