Figure 3-1 Installation clearances (unit: mm)
(1) Electric control box
Check the auxiliary facilities before installing the NetCol8000 is in position.
●
The concrete foundation provided is sufficiently strong and rigid to bear all
weight and vibration during the operation of the NetCol8000.
●
The dimensions (width and depth) of the concrete foundation are 50–100 mm
greater than the dimensions (width and depth) of the NetCol8000.
●
The surface of the concrete foundation is flat and clean.
Checking the drainage capacity
There is a drainage ditch with sufficient drainage capacity around the foundation.
NO TICE
● The design and installation of the condensate water trap must meet the
requirements shown in
.
● The layout and installation of water pipes facilitate the maintenance of the
NetCol8000.
NetCol8000-E220 Modular Indirect Evaporative
Cooling System
User Manual
3 Installation Guide
Issue 06 (2020-08-19)
Copyright © Huawei Technologies Co., Ltd.
26