Start-Up Checklist
Chk
Requirement
Comments
Initials
•
Ensure that the drive can be run and stopped freely during
the commissioning.
Stop the drive (if running), and safely HV power
from the drive.
Check the STO-IN1 and STO-IN2 circuits and connections
against a wiring diagram.
Apply +HV mains power to the drive. Energize both the STO-
IN1 and STO-IN2 circuits.
Test the operation of the STO-IN1 function when the motor is
stopped. Give a stop command for the drive (if running) and
wait for the motor to come to a standstill. While keeping STO-
IN2 energized, de-energize the STO-IN1 circuit and give a
start command for the drive. Ensure that the motor remains
at a standstill. Then, energize the STO-IN1 circuit.
Test the operation of the STO-IN2 function when the motor is
stopped. Give a stop command for the drive (if running) and
wait for the motor to come to a standstill. While keeping STO-
IN1 energized, de-energize the STO-IN2 circuit and give a start
command for the drive. Ensure that the motor remains at a
standstill. Then, energize the STO-IN2 circuit.
Restart the drive and check that the motor runs normally
Test the operation of the STO-IN1 function when the motor is
running: Start the drive and ensure that the motor is running.
While keeping STO-IN2 energized, de-energize the STO-IN1
circuit. Ensure that the motor stops. Reset any latching fault
that may have occurred (these depend on the drive’s control
mode settings). Try to start the drive. Ensure that the motor
stays at a standstill. Energize the STO-IN1 circuit
Test the operation of the STO-IN2 function when the motor is
running: Start the drive and ensure that the motor is running.
While keeping STO-IN1 energized, de-energize the STO-IN2
circuit. Ensure that the motor stops. Reset any latching fault
that may have occurred (these depend on the drive’s control
mode settings). Try to start the drive. Ensure that the motor
stays at a standstill. Then, energize the STO-IN2 circuit
Restart the drive and ensure that the drive and motor operate
normally.