Current Measurement Full Scale Calibration
a) Set programmed load current to 90 % of full load
b) Adjust R62 until output current measurement on front panel equal shunt output current
reading.
Peak Current Measurement Full Scale Calibration
a) Set programmed output current to full load
b) Adjust R64 until unit peak current measurement on front panel equals output current reading.
7.3 Non-Routine
Calibration
7.3.1
Current Limit Calibration
This calibration procedure sets the current limit trip point at the right current level. To perform a
current limit calibration, proceed as follows:
Offset Calibration
a) Apply load and set voltage to full scale, current limit to 2% of range
b) Adjust R107 until DVM output current reading matches the set current level as closely as
possible.
Full Scale Calibration
a) Set programmed output current to full scale
b) Adjust R63 until the DC supply starts going into current limit.
7.3.2
Analog Input Calibration
This calibration is performed at the factory only and should not be done by the end user unless the
controller mode has been field reconfigured.
To adjust the analog input calibration, use pot R103.
RPV Adjustment
For RPV mode, use a DVM to determine the output voltage while applying a DC input level from a
small, low noise DC reference supply. Apply some load when performing this calibration.
RPC Adjustment
For RPC mode, a load sufficient to draw 90% of available current is required. Full power is not
needed so a lower voltage than full scale can be used to perform the analog current full scale
calibration.
Содержание XDS 100-100
Страница 4: ...User and Programming Manual 4 XDS Series Electrical Safety Symbols Used in This Manual ...
Страница 27: ...User and Programming Manual XDS Series 27 Figure 3 5 Outline Drawing XDS DC Supply ...
Страница 41: ...User and Programming Manual XDS Series 41 Figure 5 4 Parallel Cable Interconnect Accessory ...
Страница 45: ...User and Programming Manual XDS Series 45 Figure 6 1 DC Power Supply Block Diagram IF option shown ...
Страница 69: ...User and Programming Manual XDS Series 69 Figure 8 3 Replaceable Fuse Locations ...