16 Standard Commissioning Process
•
License for the drive
•
Digital camera or mobile phone for taking photo
Required tools
The tools list is shown as below, for reference:
No
Name
Pictures
Descriptions
1
USB transfer Mini USB
cable (3M)
[Code: 3ABD00036680]
Communication cable,
between PC and
control panel
2
MC502 (SD memory card)
[Code: 3ABD10058698]
MC503 (SD card adaptor)
[Code: 3AFE10094795]
I/O controller
programing tool
3
USB XILINX HW-USB-II-G
(Model:DLC10)
[Code: 3ABD00034510]
Control Hub
programing tool
4
USB-5V power cable
[Code:2UBA011603R0001]
External power supply
for power module
5
Multi-Contact GRIP-CI
[Code: 3ABD00051018]
4mm Safety Test Clip
CRIP-CI; 1000V, CAT
III/16A
Содержание ACS580MV
Страница 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Страница 4: ......
Страница 8: ...8 ...
Страница 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Страница 45: ...Standard Commissioning Process 45 In this step should select Lab Tools Standalone Installation ...
Страница 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Страница 83: ...Standard Commissioning Process 83 ...
Страница 96: ...96 Standard Commissioning Process ...
Страница 121: ...Option 121 IO signals ...
Страница 122: ...122 Option Panel control interface System fault ...
Страница 140: ...140 Option ...
Страница 148: ...148 Preventive Maintenance ...