Standard Commissioning Process 25
The following has to be checked:
•
Check the main cables are well installed according to the
ACS580MV Hardware
Manual
(2UBB004520).
•
Measure the resistance of the output busbars by multimeter. The typical values would
be several ohms based on the motor data if the motor is connected.
•
Measure the resistance of the input busbars by multimeter. The typical values would
be several ohms if the TRU is connected and the MCB is not grounded, then ground
the MCB, the values would be changed to nearly zero ohm.
Содержание ACS580MV
Страница 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Страница 4: ......
Страница 8: ...8 ...
Страница 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Страница 45: ...Standard Commissioning Process 45 In this step should select Lab Tools Standalone Installation ...
Страница 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Страница 83: ...Standard Commissioning Process 83 ...
Страница 96: ...96 Standard Commissioning Process ...
Страница 121: ...Option 121 IO signals ...
Страница 122: ...122 Option Panel control interface System fault ...
Страница 140: ...140 Option ...
Страница 148: ...148 Preventive Maintenance ...