Option 117
•
Select “system” to set Marshalling parameters through the user interface as following
pictures.
System Configuration
Note:
It is important to set Par.2 number of motors at first.
More Marshalling PLC parameters, please refer to
ACS580MV Marshalling Unit
firmware manual
(2UBB005340).
•
Select “Motor1-4” and “Motor5-8” to set motors parameters according to Par.2, the
quantity of the motors
Содержание ACS580MV
Страница 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Страница 4: ......
Страница 8: ...8 ...
Страница 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Страница 45: ...Standard Commissioning Process 45 In this step should select Lab Tools Standalone Installation ...
Страница 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Страница 83: ...Standard Commissioning Process 83 ...
Страница 96: ...96 Standard Commissioning Process ...
Страница 121: ...Option 121 IO signals ...
Страница 122: ...122 Option Panel control interface System fault ...
Страница 140: ...140 Option ...
Страница 148: ...148 Preventive Maintenance ...