36 Standard Commissioning Process
Note:220V power supply and digital input and analog input should separate with each
other, it’s not allowed to use common shield cable, and every cable’s shield must be
reliably grounded.
6. Check the door interlocking system is working properly. If it is necessary, change the
electrical lock from the release position to the lock position.
7. Check remaining control signals connected the converter and also the 3rd part
equipment control signal are connected correctly and tighten. Observe the limited
contact rating of the ACS580MV I/O relays. Use the interposing relays for higher
current rated as a solution.
After checking above items, insert the plugs for X1 and BCON
,
and recover the wirings
disconnected.
Loading software and prepare DriveStartup
Loading software to all the control boards
As preparation for software downloads take the loading packages for the latest software
release and unzip the file in a separate folder on your computer.
Check the software or firmware version from the routing test report or from the parameters
group, it is not demand to upgrade the boards which have the latest version installed.
Required hardware tools and accessories
•
Personal computer with Windows 7 or Windows 10, 32 bit or 64 bit, and Office 2013 or
above version installed.
•
USB transfer Mini USB cable (3M)
•
MC502 (SD memory card)
•
MC503 (SD card adaptor)
•
USB XILINX HW-USB-II-G (Model: DLC10)
•
5.5 VDC power, USB to POF cable
Required software tools and loading package
•
T
he latest MHDRE loading package (available in
)
•
The latest
Field service report package 2.2 or newer (available in
•
Drive loader 2.1 or newer (available in
)
•
XILINX lab tools 14.3 or newer (available in
Medium Voltage Drives Portal
)
•
Drive composer pro 2.6 or newer (available in
•
DriveStartup (embedded in the Drive composer pro, activated by the commissioning
registration code)
•
Tera Term PC tool (option, available at
)
WARNING
Control power supply is not allowed to switch on until these
checking items is completed. Don’t insert plug4P&5P with power supply on!
Содержание ACS580MV
Страница 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Страница 4: ......
Страница 8: ...8 ...
Страница 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Страница 45: ...Standard Commissioning Process 45 In this step should select Lab Tools Standalone Installation ...
Страница 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Страница 83: ...Standard Commissioning Process 83 ...
Страница 96: ...96 Standard Commissioning Process ...
Страница 121: ...Option 121 IO signals ...
Страница 122: ...122 Option Panel control interface System fault ...
Страница 140: ...140 Option ...
Страница 148: ...148 Preventive Maintenance ...