ST950S Plus+ Installation and Commissioning Manual
Figure 65. Termination of Armoured Cable to CET Bar
6.6.4. Terminate the cable armouring – General Items
If required and when the detector loop tails have been terminated, the connection to the Loop Detector
Termination Board must be made with wires twisted together as pairs.
Cables can be identified as to their destinations and additional cable idents may be required on specific
contracts.
After the site cabling has been terminated, additionally check the street cables are terminated correctly
into the appropriate connectors
6.6.5. Terminate cables at the PTB (Pole Top Board)
Termination of the Feeder Cable at the Pole Top Board is recommended at this stage. This allows for
the cable testing to proceed.
for detailed information.
6.6.6. Cable Testing
If the site contains a ring cable arrangement the following test should be considered after the site has
been commissioned and while the signals are bagged;
Identify a safe position where the ring can be broken.
Page 113