ST950S Plus+ Installation and Commissioning Manual
7. Leaving Site
Before leaving site:
•
Check the current plan. If CLF is configured, use the user interface to verify that the correct plan
is in operation bearing in mind the time of day.
•
CLF and timetable can be re-synchronised with the real time clock using the user interface.
•
Reset any data that has been set up for testing, e.g. permanent demands or extensions.
•
If all inputs can be reset to normal operation, i.e. none have been set to provide permanent
signals due to faulty inputs, then use the user interface to reset all inputs to normal operation.
•
Select ‘Normal’ on the Manual Panel (unless there is a valid reason to leave it in ‘Fixed Time’, for
example).
•
Should manual control be enabled, use the user interface to enable or disable manual.
•
If all faults have been investigated the fault log may be cleared using the user interface.
•
If MOVA or UTC are enabled, ensure that they are functioning as expected.
•
Ensure the visit is accurately recorded in the controller's `visit log book'. It should contain reason
for visit, action taken (i.e. card changed etc.) and any follow up action required or details of what
actions are required should the fault re-occur.
•
Place the Junction Plan, the IC4 Printout and the Site Logbook into the pocket inside the door of
the controller.
•
Lock the Manual Panel door, ensure that the main controller door is locked and return the keys
to the customer.
Important:
The key lock should not be operated unless the screw locks are tight, i.e. Unlock the case
before undoing the screw lock and only lock the case after tightening the screw locks.
Page 131