12-7
IM AQ1200-01EN
Multi-Core Loss T
esting (Option)
3
2
1
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
App
Index
20
Master
1.
Connect the optical fiber under loss test to the optical power measurement port.
2.
Use the
rotary knob
and the
arrow
keys to select the core number of the connected fiber.
3.
Press the
Loss Test START
soft key.
The optical signal used to transmit the core number is sent to the slave.
Loss Test START
On the menu, “Loss Test START” changes to
“Loss Test STOP.”
After loss testing stops, “Loss Test STOP”
changes back to “Loss Test START
.”
Specify skipping as necessary.
Slave
4.
Connect to the light source port the optical fiber that corresponds to the core number
transmitted from the master.
It may take time to receive the core number from the master.
When the core number is received, the Loss Test START soft key is enabled.
Loss Test START
On the menu, “Loss Test START” changes to
“Loss Test STOP.”
After loss testing stops, “Loss Test STOP”
changes back to “Loss Test START.”
Optical Power Adjustment
Adjust as necessary (see section 12.4).
5.
Press the
Loss Test START
soft key.
The light turns on.
Follow steps 1 to 5 to perform a multi-core loss test.
Check marks appear over core numbers whose loss tests have been completed.
12.3 Performing a Multi-Core Loss Test