Distribution System Utility Checklist
1.
Distribution System located and mounted to floor or wall (see
Section 2.)
2.
Distribution System exhaust duct installed (if applicable),
functioning and monitored for loss of exhaust (see Section
3.7).
3.
Grounding wire installed (Distribution System and controller)
and checked for less than 1 ohm resistance (see Section 4.1).
4.
Electrical power (120/240 VAC, 50/60 Hz) connected (see
Section 4.2).
5. Remote I/O wiring installed and checked (see Section 4.4).
6.
GASGUARD Network wiring installed (if applicable) and
configured on the host (see Section 4.5).
7.
Process lines installed and helium leak tested (see Section
3.2).
8. Vent line installed and helium leak tested (see Section 3.3).
9.
Venturi line installed, leak tested and 75-95 psig (5.2-6.6
barg) of nitrogen available (see Section 3.4).
10.
Purge line installed and helium leak tested (see Section 3.5).
(If external purge cylinder utilized.)