Install the RRCU PCBs in the Base Cabinet first. Station, line and option PCBs can be mixed in
cabinets in any pattern. Do not skip slots except for vacant slots that provide RDTU or RPTU
capacity. Also, do not skip slots except for vacant slots that provide for BBKU/BDKS with
Speaker OCA. Refer to
Tables 1-54
and
1-55
. Toshiba recommends placing the RDTU, RPTU and
BDKU/BDKS PCBs first because they have special placement rules. Use the following numbered
sequence as a guide to installing the PCBs.
Important!
When placing PCBs, do not install more than five BDKU/BDKS PCBs in the same
cabinet. Five BDKU/BDKS PCBs support 80 digital telephones, which brings the
cabinet power factor to 82.25. Adding more PCBs of any type to a cabinet that has
five BDKU/BDKS PCBs may cause the cabinet to exceed it’s power factor (85
max.). See Worksheet 7.
Step 1:
Processor PCBs
•
BECU (Slot B101)/ BBCU (slot B102), are required for system operation. The BECU/BBCU
will support up to two cabinets without the BEXS/BBMS expansion subassemblies.
•
BEXS and BBMS subassembly PCBs are required for 3 to 7 cabinet systems.
•
BSIS subassembly PCB is required for SMDR and/or SMDI or Toshiba Proprietary Voice Mail
RS-232 interface.
Note
The BECU/BBCU is licensed for 64 ports and four DTMF receivers from the factory. If
more capacity is required additional licenses must be uploaded to the processor. See
“Worksheet 9 – Software Licenses” on page 1-52
.
Step 2:
Remote Cabinet PCBs
•
RRCU PCBs installed in the main location must be placed in Base Cabinet slots S102~S108 in
any order. Before installing other PCBs make sure there is a Base Cabinet slot available for
each RRCU PCB needed. An RRCU may occupy a vacant slot adjacent to RDTU or RPTU. An
RRCU PCB in a remote location can support one or two remote cabinets and can be installed in
any slot of either cabinet.
The number of RRCU PCBs required in the Base and Remote Cabinet locations is shown in
Table 1-52
:
Table 1-52
Main Processor PCB/ Remote Cabinet Configuration
RRCU PCBs
Needed in
Base Cabinet
Remote Cabinet Configuration
RRCU PCBs Needed at
Remote Location (s)
1
1 or 2 Remote Cabinets in one location
1
2
2 to 4 Remote Cabinets in two locations or 3 to 4
Remote cabinets in one location.
2
3
3 cabinets if cabinets are in separate remote locations.
3
4
4 cabinets if cabinets are in separate remote locations.
4
5
5 cabinets if cabinets are in separate remote locations.
5
6
6 cabinets if cabinets are in separate remote locations.
6
Summary of Contents for Strata CTX100
Page 16: ...Introduction Related Documents Media xii Strata CTX I M 10 02 ...
Page 94: ...Strata CTX100 Installation Installing the CTX100 Cabinet 2 24 Strata CTX I M 10 02 ...
Page 150: ...Strata CTX670 Installation Remote Expansion Cabinet Unit 3 56 Strata CTX I M 10 02 ...
Page 188: ...PCB Installation Network Requirements 4 38 Strata CTX I M 10 02 ...
Page 238: ...T1 Loop Back Testing 6 12 Strata CTX I M 10 02 ...
Page 310: ...Station Apparatus 2000 series Telephones 8 48 Strata CTX I M 10 02 ...
Page 342: ...Peripheral Installation Station Message Detail Recording SMDR 9 32 Strata CTX I M 10 02 ...