60
Installing Battery Cables (continued)
4.
NEGATIVE BATTERY CABLE
NOTE: Do not attach both the positive and the negative cables to a single battery. For best results, attach the
positive cable to the first battery and the negative cable to the last battery as shown.
a.
Route the negative cable from the TriPac ENVIDIA battery box to the tractor’s negative battery
terminal, cut to length and strip 1/2 to 3/4 in. (13 to 19 mm) of insulation from cable end.
b.
Slide the supplied
BLACK
heat shrink tubing and terminal ring onto the end of the cable. Attach the
terminal ring firmly to end of cable.
c.
Position heat shrink tubing to cover exposed wires on the terminal ring and use a heat gun to shrink
the tubing in place.
d.
Install the negative cable terminal lug onto the battery’s
NEGATIVE (-)
connection and tighten
securely.
e.
Apply Superlube (PN 203-524) or equivalent onto the battery’s connection.
5.
TriPac Envidia BATTERY BOX
a.
Connect positive cable terminals to each of the batteries.
b.
Connect negative cable terminals to each of the batteries.
6.
INSTALL FUSE (F13)
a.
Remove the nuts from the fuse holder, place the 175 amp fuse onto the studs, and on top of the
battery cables lugs and reinstall the nuts. Tighten the nuts to 120 in-lb (13.5 N•m).
b.
Close the fuse holder cover securely.
c.
The TriPac ENVIDIA system is now powered.
Figure 34: Installing Battery Cables and Fuse
Summary of Contents for TriPac Envidia
Page 2: ......
Page 11: ...9 Battery Box Dimensions Figure 1 Battery Box Dimensions...
Page 12: ...10 Battery Box Dimensions continued Figure 2 Battery Box Dimensions continued...
Page 13: ...11 Evaporator Control Box Dimensions Figure 3 Evaporator Control Box Dimensions...
Page 14: ...12 Condenser with Receiver Drier Dimensions Figure 4 Condenser with Receiver Drier Dimensions...
Page 15: ...13 HMI Dimensions Figure 5 HMI Dimensions...
Page 16: ...14 1000 Watt Power Inverter Dimensions Option Figure 6 1000 Watt Power Inverter Dimensions...
Page 18: ...16 D2 D4 Heater Dimensions Option Figure 8 Heater Dimension...
Page 19: ...17 BLANK PAGE...
Page 21: ...19 Typical Component Locations Figure 9 Typical Component Locations...
Page 45: ...43 A C Duct Installation continued FLUSH MOUNTED EVAPORATOR Figure 21 A C Duct locations...
Page 76: ......
Page 77: ......
Page 78: ......
Page 79: ......