PROFIBUS DP communication module
9.6 PROFIBUS DP commissioning using the GSD file in STEP 7 (example)
3RW44 soft starters
Manual, 03/2017, NEB535219502000/RS-AB/008
165
Requirements for commissioning
Table 9- 2
Requirements for commissioning
Prior activity
For more information, see ...
1. Soft starter has been installed
Chapter Installation, connection and feeder
configuration (Page 29).
2. PROFIBUS DP communication module has
been installed
Chapter Installing the PROFIBUS DP
communication module (Page 153).
3. The station address has been set on the soft
starter
Chapter Activating the PROFIBUS DP
communication module (fieldbus interface) and
setting the station address via the device
interface using the "Soft Starter ES Premium" or
the "Soft Starter ES Smart + SP1" software
(Page 160).
4. The soft starter has been configured
(configured and parameterized)
Chapter Configuring soft starters (Page 162).
5. The supply voltage for the DP master is
switched on
DP master manual
6. The DP master is switched to the RUN
operating state
DP master manual
9.6.2
Configuration using the Device Master Data (GSD) in STEP 7
Table 9- 3
Commissioning
Step
Description
1
Activate the PROFIBUS DP communication module as described in chapter Activating
the PROFIBUS DP communication module (fieldbus interface) and setting the station
2
Set the required station address as described in chapter Activating the PROFIBUS DP
communication module (fieldbus interface) and setting the station address (Page 156).
3
Switch on the supply voltage for the DP master CPU 315-2 DP at the infeed module.
4
Observe the status LEDs of the DP master CPU 315-2 DP on the infeed module:
5 V DC: Lights up
SF DP: Off
BUSF: Flashing
5
Start the SIMATIC Manager and create a new project with a DP master (e.g. CPU315-
2 DP with DI 16 x DC 24 V and DO 16 x DC 24 V). Generate OB1 and OB82 for the
project.