6.4.2.3 SEAR IIi Setup
Review the program in the GCP5000 (GCE) by using the left or right arrows on the Display
module and scrolling to the Program View screen, then scrolling down to or selecting
3) SEAR
Programming
menu.
Figure 6-14 Program View – SEAR Programming
NOTE
The Control Descriptor Language (CDL) used to customize the SEAR’s
operation, settings, and behavior can differ between railroads.
Refer to the specific SEAR IIi Configuration Summary document for
details of application CDL program, LEDs, and Alarms. The ATCS
address must be entered prior to the SEAR IIi communicating with the
CPU Module.
Prior to beginning the SEAR IIi setup procedure, have circuit plans
showing the SEAR IIi setup page available for reference.
Site Setup must be run in its entirety. Setup may be accomplished either
using the Display module or the WebUI.
The first nine (9) parameters, appearing on the first page of the SEAR Program Menu, are as
follows:
0) Menu
1) Application(CDL)
2) Digital Inputs
3) Analog Inputs
4) Non-Vital Outputs
5) Echelon Modules
6) Communication
7) Serial Ports
8) Set to Defaults
9) SEAR Setup