Installation of the WiMag Communications Rack
13.1 Overview
The 3U and 2U racks should be assembled in accordance with general assemblies
667/GA/47260/200 and 667/GA/47260/300 respectively. They can be installed into a
controller from the Factory or retrofitted into existing controllers. All components required
for installation will be included with assembled racks.
13.2 Installing the PoE Switch
Note
: The PoE switch should normally be pre-installed in the communications rack,
variant /100 only.
1. The 8 port PoE switch is slid down the DIN rail and secured with a terminal block
end stop.
2. Connect a non-PoE Ethernet port to the user maintenance Ethernet port using a
supplied Ethernet cable.
Figure 51 : 8 Port PoE Device showing two free non-PoE ports
(numbered 1 and 2)