Commissioning
6.1
Launching the TDC devices
Establish the voltage supply for the TDC devices. All sensors connected to the TDC device
will then also be supplied with voltage.
Operational readiness after 60 seconds
The TDC device is ready for operation after approximately 60 seconds.
▸
Check the operational status of the TDC device by looking at the status indicators.
6.2
Preparing the configuration PC
6.3
General notes
HAZARD
Disconnecting the power to the system
▸
Make sure that all the components of the gateway system are disconnected from the
power supply during the electrical installation work.
HAZARD
Risk of injury due to electrical current
▸
Standard safety requirements must be met when working on electrical systems.
▸
The power supply must be disconnected when attaching and detaching electrical
connections.