Installation and Operation Manual
Page 86 of 156
[PVI-XXX.0-YY(-TL) - Rev:1.0]
11.7.5
Connection for the on and
off command of the single 55kWp
modules.
With reference to Table Figure 11-11 and
Table 11-4, it is possible to control, by
pressing the REMOTE n signals, the mains
connection or otherwise of the single
modules.
By default, all REMOTE n signals are
connected to earth (X9) via jumpers with
screws on the terminal block. These must be
removed if a you wish to make a manual
connection, for example via a clean relay
contact.
NOTICE
Do NOT connect signals under voltage to the
REMOTE n clamps, otherwise the circuits of
the modules will be irremediably damaged.
These must be exclusively open or
connected to X9 or other clean contact.
NOTICE
It is important to leave a gap of 30 cm of
cable pocketed in the ACBOX to allow the
full extraction of the AC drawer
.
Capitolo §17.7
11.7.6
Setting of the
communication addresses.
Put the QS2 switch in ON position (up):
if the auxiliary line is under voltage, all
the present displays will be turned on.
Set from the display (Figure 13-3) a
different RS485 address on every
module, according to the following
indications:
•
If the 485 line is connected to a single
tower, set a different address on every
module of the tower.
•
If the 485 line is connected to more
than one tower, set a different address
on every module of each tower.
Chapter §13
MAKE SURE THAT THERE ARE NO
SIMILAR 485 ADDRESSES IN THE
SYSTEM.
THIS
MAY
CAUSE
COMMUNICATION CONFLICTS.
11.7.7
Final checks.
Close the front panels, taking care that
the handles, if present, are positioned
on 0 (OFF) and insert and tighten the
screws.
Close all the other panels, after first
reconnecting the respective earth cable
to the inverter casing.