Commissioning
25
SMO 10
■
Disconnect the charge pump electrically.
■
Select Service in menu 8.1.1, Menu type.
■
Select Yes in menu 9.3.2, Electric boiler.
■
Select “0” in menu 9.1.2, Number of FIGHTER
2010
■
Follow the instructions set out in Commissioning
2 0 1
1 3 2
Settings at start up with
FIGHTER 2010 / 2005
■
In channel 20 select the address number in ques-
tion. Confirm with the Enter button.
The address number should be selected so that each
FIGHTER 2010 / 2005 in the system has a unique
address (19) for communication with SMO 10.
For example, three FIGHTER 2010s / 2005s in the
same system give the addresses 1, 2 and 3. The
FIGHTER 2010 / 2005 that produces hot water should
be set to 1.
■
Now restart FIGHTER 2010 / 2005 with the isola-
tor switch or the miniature circuit-breaker
■
SMO 10 should be voltage fed within 5 minutes
after the FIGHTER 2010 / 2005 has been restart-
ed, to prevent communication alarms.
■
When FIGHTER 2010 / 2005 is connected to
SMO 10, the FIGHTER 2010 / 2005's values
should be changed in SMO 10
When more than one FIGHTER 2010 / 2005 is
connected they all receive the same values.
■
Channel 13 should be set to 2.
Confirm with the Enter button.
■
Select Service in menu 8.1.1, Menu type.
■
Set menu 8.3.1, Fuse size, equal to the property's
main fuse.
■
Select the number of FIGHTER 2010s / 2005s in
menu 9.1.2.
■
Follow the instructions set out in Commissioning
■
Select type of docking in menu 9.2.3.
■
Set the required operating mode with the operat-
ing mode button.
■
Set the charge flow for hot water production.
Check
∆
T in menu 5.15, Difference flow-return.
■
See the section Room temperature — Default set-
ting to set the curve slope and offset heat curve.
FIGHTER 2010/2005
SMO 10
NOTE!
Type of docking and Number of
FIGHTER 2010s / 2005s should be
entered in the Setting table.
Start up settings without
FIGHTER 2010 / 2005
Commissioning
■
8.1.1, Menu type: Select Service to access the
entire menu system.
■
9.3.9, Operating mode Shows the operating sta-
tus of SMO 10.
■
5.2, HP operating status: Shows the operating
status of F-2010/2005.
■
5.3, Compressor status: Shows the compressor
status in F-2010/2005.
■
5.4, Minutes to start: Shows the time to the com-
pressor start in F-2010/2005.
Menus to remember
Summary of Contents for SMO 10
Page 1: ...R MOS GB 0521 1 511262 SMO 10 INSTALLATION AND MAINTENANCE INSTRUCTION SMO 10...
Page 2: ......
Page 50: ...Electrical circuit diagram 48 SMO 10 Sheet 1 4...
Page 54: ...Dimensions 52 SMO 10 405 406 151 5 328 276 Dimensions and setting out coordinates...
Page 58: ...SMO 10 56...
Page 59: ......