Hardware installation
21 / 156
PHASES / ONLY FOR LOAD MANAGEMENT MODE
DSW1.3 to DSW1.5
Function
DIP-switch
Figure
Supply (phases)
D1.3
ON=
only 1
phase
OFF= all
3
Phases
Phase assignment (*)
D1.4
D1.5
Figure
Phase
L1
at terminal 1
connected
OFF
OFF
ON
OFF
Phase
L2
at terminal 1
connected
OFF
ON
Phase
L3
at terminal 1
connected
ON
ON
(*) Comments:
For load distribution in single phase operating mode any phase (L1, L2 or L3) of the mains supply line can be
connected to the connection terminal 1.
The determination of which phase of the mains supply line was connected serves for informing the (optional)
load management software in order to facilitate an efficient and proper load distribution.
Summary of Contents for KeContact Series
Page 1: ...KeContact Load Management System manual...
Page 151: ...Appendix 151 156 7 3 Data sheet power supply TDK Lambda DPP50 Dimensions...
Page 152: ...Appendix 152 156...
Page 156: ......