IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide
3 Maintenance
Issue 01 (2016-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
22
Item
Method
Expected Result
Troubleshooting
Battery pack
charging and
discharging.
Ensure that both the
battery packs and
the AC mains
supply are operating
normally. When the
UPS is working in
online mode,
disconnect the AC
supply, which
switches the load to
the battery supply.
After the battery
pack voltage drops
to around 450 V,
restore the AC
mains supply,
enabling the UPS to
recharge the battery
packs in equalized
mode. Check
whether the battery
pack capacity is
normal.
When the AC supply is
disconnected, the battery
packs automatically
begin to carry the load.
When the AC supply is
restored after the battery
pack voltage drops to
approximately 450 V, the
UPS begins to recharge
the battery packs in
equalized mode.
None
UPS parameter
settings.
Check whether
the battery pack
capacity is
correctly set.
Check whether
the charge
current is
correctly set.
The capacity of
battery packs
connected to a single
UPS is set to the
required value.
The battery pack
charge current is set
to 0.1 C.
If any UPS parameter
settings are incorrect, set
the parameters based on
onsite battery pack
configurations.