4.1 Installing Cables (ECC800 Scenario)
Context
This section describes how to connect the CIM communications cable to the smart ETH
gateway in the ECC800 scenario.
Connect the Hall effect sensor on the positive battery string terminal side to the HALL_1
current monitoring port on the CIM, and connect the Hall effect sensor on the negative
battery string terminal side to the HALL_2 current monitoring port on the CIM.
The positive and negative battery string cables must be routed in directions shown by
arrows on the Hall effect sensors. The positive battery string cable routes from the UPS to
the battery, and the negative battery string cable routes from the battery to the UPS.
Figure 4-1
CIM and BIM networking