4-51
4.15.3 Repairing method for the makeup pump
1 Remove the tube connecting block of makeup reservoir, and then connect
the cleaning bottle to the pipe of pipe N.
(You can apply pressure more easily by putting a tube between the pipe
and the cleaning bottle.)
2 Operate the pump and then MV7 on the “Solenoid Valve/Pump Test” screen.
3 Apply pressure with the cleaning bottle.
4 When the makeup of the hand pump flows to the pipe N, the repair work is completed.
If the pump cannot be repaired with the cleaning bottle, use the hand pump.
(Refer to 4.15.2 Repairing method for the supply pump.)
Such a hard sticking which cannot be repaired with the hand pump will not occur.
4.15.4 Procedure for repairing the circulation pump
1 Start the circulation pump by “Start up” or “Eject ink”.
2 When the circulation pump is started, operate it for about 10 minutes with the pressure
adjusting screw turned completely clockwise to obtain the maximum pressure.
3 Stop the pump and then execute “Nozzle Backwash”. If suction from the nozzle is
confirmed, the repair work is completed. If the pump is not repaired, repeat the same
operations starting from 1 again. If the pump cannot be repaired after these steps of 1 2
3, 2 or 3 times, replace the pump unit.
4.15.5 Procedure for repairing the recovery pump
1 Operate the pump, MV1, and MV6 in this order on the “Solenoid Valve/Pump Test”
screen.
2 Operate the pump with the pressure adjustment screw turned completely
clockwise to obtain the maximum pressure.
3 If the ink flows into the recovery tube, the repair work is completed.
If the pump cannot be repaired by pump operation for 10 minutes, replace the pump unit.
Pipe
Pipe N
Cleaning bottle
Summary of Contents for IJ UX
Page 1: ...Service Manual HITACHI Printer Model UX Revision July 1 2015 Version ...
Page 2: ... Revision of UX service manual Revision Chapter Revised Page Frist Edition ...
Page 15: ...1 9 2 External views Rear side 1 2 2 Main body internal Appearance with inner cover T removed ...
Page 16: ...1 10 1 2 3 Print head UX E UX D B Air exhaust port ...
Page 107: ...3 27 Circuit diagram of EZJ127A ...
Page 108: ...3 28 Circuit diagram of EZJ127B ...
Page 122: ...3 42 Circuit diagram of EZJ129 ...
Page 131: ...3 51 3 3 20 Electrical Connection Diagram ...
Page 132: ...3 52 ...
Page 188: ...4 55 5 Reset the time of the R air filter to 0 on the Parts usage time management screen ...
Page 301: ...7 Attached Drawing 7 1 Circulation System Diagram Circulation System Diagram UX B D 7 1 ...
Page 302: ...Circulation System Diagram UX E 7 2 ...
Page 305: ...7 5 7 2 2 Electrical Connection Diagram UX B Basic model Electrical Connection Diagram UX B ...
Page 308: ... Nozzle diameter 65μm 7 8 7 4 Dimensions around charge electrode and deflection electrode ...