Sequestering on the Cell Saver 5+ System
P/N 53063-50, Manual Revision: B
7-4
Step 7:
Install the large bore tubing on the sequestering harness into the
effluent line sensor by grasping the distal (towards the bags) con-
nection tubing stop and using a “flossing” motion, pull the tuning
down through the sensor until the bowl end connection tubing stop
reaches the upper end of the effluent line. Ensure that this large-
bore tubing is fully seated in the line sensor groove along its entire
length.
Step 8:
Close the centrifuge cover.
Step 9:
Hang the collection bag with yellow-striped tubing onto one of the
waste bag posts on the Cell Saver 5+. Hang the collection bag with
blue-striped tubing onto another waste bag post. Hang the air bag
on the remaining post.
Step 10:
Close the red clamps on the product bags and ensure that the tub-
ing and cap connections to the product bags are secure.
Step 11:
Ensure that the white product bag clamps are open.
Setting the
Parameters
Note: The sequester protocol is only available when the unit is first powered ON.
Warning: prior to undertaking sequestration on the CS5+, the operator should be
familiar with the operating instructions for the CS5+ and any associated
precautions and warnings in addition to any precautions and warnings included
in this chapter specific to the sequester procedure.
1. Press START and the current settings screen will appear:
CURRENT SETTINGS
Press START to begin procedure
Press MODIFY to change settings
Min Wash Vol. - 225:
-125:
Reservoir Level:
Resume at Level:
Reservoir Level Sensor:
Pump Regulation:
Empty RBCs to:
AUTOMATIC
Press YES to restore default settings
NO WASH
NO WASH Option:
Protocol:
OFF
Cell Saver
1000 ml
750 ml
800 ml
400 ml
ON
ON
Blue Line