Markings
Before coupling the chambers and column, check that the markings on the
breaking chambers correspond with those on the column
Time taken for
coupling operation
The final chamber/column coupling operations should be completed in a
time of
40 min.
NOTE: The coupling operations must be carried out by a mini-
mum of two people.
T(max)
40 min
Lifting means
Provide an adequate means of hoisting:
3,000 daN
(minimum)
H + 2 m
H
H +1 m
Stages of the
coupling operation
The chamber- column coupling operation can be broken down into a num-
ber of stages:
Step
Subject
Page
A
Positioning the chamber casing
2
B
Preparing the breaking chambers
3
C
Preparing the column’s corona shield
4
D
Preparing the elements required for the coupling opera-
tion
5
E
Hoisting and preparing the column
7
F
Final coupling
8
Summary of Contents for SF6
Page 206: ...Grid Solutions This page is intentionally blank...
Page 212: ...Grid Solutions This page is intentionally blank...
Page 216: ...Grid Solutions This page is intentionally blank...
Page 220: ...Grid Solutions This page is intentionally blank...
Page 299: ...GE Information This page is intentionally blank...
Page 300: ......