4.4 Completing the Installation
This section explains how to verify correct installation of the RRD/TLZ07 dual
ISE drives by performing the power-on self-test (POST).
Section 4.4.1 describes the POST for a CD–ROM drive.
Section 4.4.2 describes the POST for a TLZ07 tape drive.
4.4.1 RRD CD-ROM Power-On Self-Test
Use the following procedure to execute the POST:
1.
Power on the system.
•
The Busy indicator flashes for approximately 10 to 20 seconds.
Successful POST
After successful completion of the POST, the Busy indicator shuts off.
Have the system manager restart the operating system and assign a device
name to the CD–ROM drive.
Unsuccessful POST
If the Busy indicator remains on continuously then the POST failed.
p
Attempt to clear the failure by powering off the system and then re-
executing the POST.
p
Check to be sure the CD is not loaded upside-down.
p
Check and reseat all ISE cable connections.
p
If the failure continues, refer to the appropriate system troubleshooting
and diagnostics manual (Appendix A).
4–6 RRD/TLZ07 Dual ISE Drives